A $27 million expansion of a section of U.S. Highway 53 near Cook to four lanes leads the list of state highway projects announced today for the northeastern district of the Minnesota Department of Transportation.
In all, the district will undertake just over $70 million in construction: $52.7 in new projects and $17.3 million in funding carried over from 2006.
"We're going to be doing a lot of work this summer -- more than 100 miles of road," District 1 spokesman John Bray said.
But the backlog of needed work is growing, Bray said.
"We do what we are able to do with the funding provided us," he said.
ADVERTISEMENT
This summer's District 1 projects include:
1. Location: Highway 53 (St. Louis County)
Description: 4-lane expansion, DWP railroad bridge to 4.1 miles south of Cook
Construction costs: $27 million
Traffic impacts: Daytime single-lane closure under flagger control for entire project.
2. Location: Highway 35 (Pine County)
Description: Chisago/Pine County line to Hinckley
Completion date: November
ADVERTISEMENT
Construction costs: $13 million
Traffic impacts: Single-lane traffic. Short-term bypass.
3. Location: Highway 169 (Itasca County)
Description: Bovey bypass four-lane expansion
Completion date: July 2008
Construction costs: $13.1 million
Traffic impacts: Daytime single-lane closure for entire project.
4. Location: Interstates 35, 535 and U.S. Highway 53 (St. Louis County) in Duluth
ADVERTISEMENT
Description: Bridge rail replacement, safety improvements, concrete pavement repairs
Completion date: November
Construction costs: $6.5 million
Traffic impacts: Detour
5. Location: Highway 1 (Lake County) from New Tomahawk Road to Lake County Hwy 2.
Description: Kawishiwi River bridge replacement
Completion date: October
Construction costs: $6.3 million
Traffic impacts: Daytime single lane closure for entire project. Detour for short time periods. Bridge constructed with bypass, single lane stop and go.
6. Location: Hwy 61 (Lake County) near Silver Bay
Description: Reconstruction
Completion date: November
Construction costs: $6 million
Traffic impacts: Traffic bypassed adjacent to work zone
7. Location: Hwy 53 (St. Louis County) in Duluth at Trinity Road
Description: Reconstruction
Completion date: October
Construction costs: $5.7 million
Traffic impacts: Traffic bypassed adjacent to work zone
8. Location: Hwy 169 (Itasca County), Pokegama Causeway Bridge
Description: Bridge construction with bypass
Completion date: July
Construction costs: $5.5 million
Traffic impacts: Daytime single lane closure for entire project.
9. Location: Hwy 35 (Carlton and St. Louis counties) from Mahtowa to Highway 210 and Thompson Hill in Duluth.
Description: Mill and overlay, Concrete repair
Completion date: September.
Construction costs: $5.2 million
Traffic impacts: Daytime and over night lane closures
10. Location: Highhways 18, 23, 48, 70, 123 (Pine County)
Description: Culvert replacement, bituminous mill and overlay
Completion date: November
Construction costs: $5 million
Traffic impacts: Single-lane traffic with flaggers.
11. Location: U.S. Highway 2 (Itasca County)
Description: Cohasset urban design and reconstruction.
Completion date: June
Construction costs: $3 million
Traffic impacts: Daytime single-lane closure for entire project.
12. Location: Highway 210 (Carlton County), Cromwell to I-35
Description: Culvert replacement, bituminous mill and overlay
Construction costs: $2,500,000
Traffic impacts: Single lane traffic with flaggers and pilot car
13. Location: Highway 61 (St. Louis and Lake Counties), London Road in Duluth, Two Harbors
Description: Mill and overlay
Completion dates: July 2006 to Oct. 2006
Construction costs: $1.5 million
Traffic impacts: Detour on London Road. Lane closures in Two Harbors.
14. Location: Various highways across the district
Description: Crack Sealing
Completion date: September
Construction costs: $1 million
Traffic impacts: Daytime single lane closure for entire project.
15. Location: Various highways across the district
Description: Culvert replacement
Construction dates: September.
Construction costs: $1 million
Traffic impacts: Occasional shoulder closures
16 Location: Highway 2 (Itasca County) at Prairie River Bridge, etc.
Description: Bridge Replacement
Completion date: July
Construction costs: $838,600
Traffic impacts: Daytime single lane closure under flagger control
17. Location: Highways 1, 135, 169 (St. Louis County)
Description: Turnlanes and culvert replacements
Completion dates: August
Construction costs: $700,000
Traffic impacts: Daytime single-lane closure under flagger control for entire project. Bridge con-structed with bypass.
18. Location: Highway 61 interstates 35 and 535 (St. Louis and Lake Counties), North Shore to Duluth
Description: Tunnel alarms
Completion dates: November
Construction costs: $523,000
Traffic impacts: Daytime lane closures
19. Location: Highway 70 (Pine County), near Rock Creek
Description: Bridge and culvert replacement
Completion date: September
Construction costs: $425,000
Traffic impacts: Detour
20. Location: Highway 35 (St. Louis County) Scanlon to Boundary Avenue
Description: Sign replacement
Completion date: October.
Construction costs: $350,000
Traffic impacts: Daytime lane closures
21. Location: Highway 38 (Itasca County) North of Grand Rapids
Description: Landscaping
Completion date: Fall
Construction costs: $172,000
Traffic impacts: None
22. Location: Interstate 535 (St. Louis County), Blatnik Bridge
Description: Deck seal
Construction costs: $100,000
Traffic impacts: Daytime lane closures