Bridge work to divert Seven Bridges Rd. traffic

Seven Bridges Road will be closed to through traffic beginning Monday as two bridges are rebuilt. Northland Constructors of Duluth will replace bridges one and eight. Bridge one is the southernmost bridge on the road, crossing Amity Creek on Occi...

Seven Bridges Road will be closed to through traffic beginning Monday as two bridges are rebuilt.

Northland Constructors of Duluth will replace bridges one and eight. Bridge one is the southernmost bridge on the road, crossing Amity Creek on Occidental Boulevard. Bridge eight is on Skyline Parkway just south of the Maxwell Road intersection.

The road will remain open between the bridges during the summer, with access via Maxwell Road.

Seven Bridges Road is expected to reopen to through traffic in mid-November. All work on the bridges will be complete by July 2008.